Answer:
The best production speed = 300ft/minute
18000/10 = 1800ft/part hr
Step-by-step explanation:
Cut Speed A = 100ft/minute
Cut speed B = 200ft/minute
Cut speed C = 300ft/minute
Since 60 minutes = 1 hour
Machine works for one hour
Total length with cut for speed A = 60* 100 = 6000ft
Total length with cut speed B = 200 *60 = 12000ft
Total length with cut speed C = 300 * 60 = 18000ft
Number of 8 part in length A = 6000/8 = 750ft/part hr
Number of 12 parts in length B = 12000/12 = 1000ft/part hr
Number of 10 parts in length C =
18000/10 = 1800ft/part hr