The probability of completing a project in a specified amount of time is being calculated. For a particular path through the project, the ______________ shows the path’s number of standard deviations that the specified time is past the expected path completion time.

1) m-value
2) z-value
3) sigma-value
4) s-value
5) alpha-value

User Cleggy
by
8.3k points

1 Answer

3 votes

Answer: 2). z-value

Explanation: the z- value is a statistical tool used to measure the deviations of the standard deviation above or below the population mean,it can also be placed on a normal distribution curve.It used to calculate the probability of a value appearing within the normal distribution curve,it can also be used to determine the percentage of people participating in a given activity like the time it takes to complete a given task/ project by different persons.

User Raeesh Alam
by
8.0k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.