Answer:
- No job uses more than one machine simultaneously .
- No machine processes more than one job simultaneously.
- Only 3 hours will be needed to complete the jobs.
Step-by-step explanation:
However, Job 2 can be completed at time 3 which is late by 1 hour.
Suppose that the processing times are exponentially distributed.
Let
- The processing rate of job j on machine 1
- The processing rate of job j on machine 2
Expected make span is minimized by processing the jobs in the descending (high to low) order of processing
Make span is the completion time of the last job processed. Although make span is defined as a completion time of a job, it actually measures how long the production facility should remain open.