Answer:
$2.10
Step-by-step explanation:
The computation of the cost per equivalent unit for direct material is shown below:
= (Direct material cost + Beginning inventory cost) ÷ (equivalent units for the materials)
where,
Equivalent units would be
= Completed and transferred units + beginning work in progress units + additional units
= 25,000 + 110,000 + 30,000
= 165,000 units
And, all the other things would remain the same
= ($253,000 + $93,500) ÷ (165,000 units)
= $2.10
Since all the units are completed with 100% and we consider it same