Answer:
Overhead absorption rate
= Budgeted overhead x 100
Budgeted direct labour cost
= $400,000 x 100
$2,000,000
= 20% of direct labour cost
Overhead applied
= 20% x $1,800,000
= $360,000
The balance in the factory overhead account is $360,000 debit
The correct answer is B
Step-by-step explanation:
In this case, we need to calculate the overhead application rate, which is the ratio of budgeted overhead to budgeted direct labour cost multiplied by 100. Overhead applied is calculated as overhead application rate multiplied by actual direct labour cost.