Scheduled receipts differ from planned receipts in that scheduled receipts:

have not been pegged with actual customer orders.

have longer lead times.

involve orders that have already been placed.

involve orders that have not yet been placed.

involve exceptions to order quantity policies.

User Camila
by
5.1k points

1 Answer

4 votes

Answer:

involve orders that have already been placed.

Step-by-step explanation:

Scheduled receipts are purchase orders or replenishment orders that have assigned due dates. The items required should be received in a particular time period, that is why we refer to them as scheduled.

Scheduled receipts are part of the material requirements planning (MRP) records.