Answer:
5,220 hours
Step-by-step explanation:
Lets summarize the information first,
Actual Hours = 5,140
Actual Indirect labor cost = $2,056
Spending Variance = $257 Unfavorable
Activity Variance = $28 Favorable
We can reverse work for budgeted labor hours, first for the standard rate,
Spending variance = Actual hours * Standard rate/hour - Actual Overheads
-257 = 5140x - 2056
x = (2056-257)/5140
x = 0.35/hour (This is the standard over head rate )
Activity Variance = Standard rate*Standard hrs - Standard rate*Actual Hrs
28 = 0.35y - 0.35*5140
Solving for y,
y = 1827/0.35
y = 5,220
So budgeted hours for Stolen Horse Corporation were = y = 5,220 hours