Answer:
B. $30,000 and $15,000
Step-by-step explanation:
We can compute this as follows,
We need to calculate flexed budget costs for the production of 125 boots.
Budgeted / boots are as follows,
Leather cost / boot = $240
Direct Labor / boot = $120
The costs that should have been for 125 boots are then,
Leather = 125 * 240 = $30,000
Direct Labor = 125 * 120 = $15,000