Ben needs to write a progress report. In his progress report, which order should Ben place the following points? 1) The project team has finalized their first drafts. II) As of January 31, the project is on budget but two weeks behind schedule. III) The schedule was setback due to unexpected snow

closing the office. IV) Spending is on track with the budget.
A. IV, I, I, II
B. II,IV,I,III
C. I,IV,III,II
D. III,I,II,IV​

1 Answer

4 votes

The following is the order,

II) As of January 31, the project is on budget but two weeks behind schedule.

IV) Spending is on track with the budget.

I) The project team has finalized their first drafts.

III) The schedule was setback due to unexpected snow

closing the office.

Option B - II,IV,I,III

Explanation:

As of January 31, the project is on target but two weeks off schedule. Expenditure is on track. The project team has completed their first drafts the project team has finished its first drafts. The schedule has been established back due to the sudden snow closure of the office.

An assessment carried out during a project or process that includes information, such as the accomplishment of the goals, the money spent, the challenges and whether the project or process should be carried out in good time and in the budget.

Management uses progress reports to assess whether improvements in an ongoing effort are appropriate.