A factory produces 130,000 televisions per quarter. A total of 9,000 production hours are used by the factory per quarter.

Compute the velocity in units per hour.

(Note: Round answer to two decimal places.)
a. 16.50 units per hour
b. 15.50 units per hour
c. 14.44 units per hour
d. 18.45 units per hour

User Uriel
by
6.6k points

1 Answer

1 vote

Answer:

Option (c) is correct.

Step-by-step explanation:

Given that,

Factory produces = 130,000 televisions per quarter

Total production hours used by the factory per quarter = 9,000

Therefore,

Velocity of units per hour = (Number of units produced ÷ Time taken to produce those units. )

Velocity of units per hour = (130,000 units ÷ 9,000 hours )

Velocity of units per hour = 14.44 units per hour