Answer:
A: Yes
Step-by-step explanation:
The additional worker would cost $100 per day i.e. Marginal Cost = $100
Whereas the Marginal Revenue = (2,750-2,600) = $150
Since Marginal revenue exceeds marginal cost by (150-100) = $50, Cindy should hire 12th worker.