Answer:
Labour rate variance
= (Standard rate - Actual rate) x Actual hours worked
= ($12 - $13) x 320,000 hours
= $320,000(U)
The correct answer is C
Step-by-step explanation:
Labour rate variance is the difference between standard labour rate and actual labour rate multiplied by actual labour hours worked.