69.8k views
1 vote
Consider a project with free cash flows in one year of $90,000 in a weak economy or $117,000 in a strong economy, with each outcome being equally likely. The initial investment required for the project is $80,000, and the project's cost of capital is 15%. The risk-free interest rate is 5%.

The NPV for this project is closest to:
A) $6,250
B) $14,100
C) $10,000
D) $18,600

1 Answer

1 vote

Answer:

The NPV for the project will be $6000 which is not in the given option

Step-by-step explanation:

We have given the project has free cash flows in one year of $90,000 in a weak economy

Project cash flow at the end of year 1 in weak economy =
C_(1weak) $ 90,000

Cash flows to lenders,
C_L = FV of debt = Debt x (1 + interest rate) = 80,000 x (1 + 0.05) = $ 84,000

Hence cash flows to equity holders =
C_(1weak) -
C_L = 90,000 - 84,000 = $ 6,000

So the NPV for the project will be $6000 which is not in the given option

User Aerion
by
4.9k points