Answer:
$335,000; $1,425,000
Step-by-step explanation:
Record cost of the land as follows:
= Cost of purchasing parcel of land + Demolition of old building + Legal fees - value of Salvaged materials sold
= 320,000 + 20,000 + 5,000 - 10,000
= $335,000
Record cost of the new building as follows:
= Architect's fees + Construction costs
= 35,000 + 1,390,000
= $1,425,000