Oliver needs to purchase new equipment for his team in order to complete his

project on time. His budget for purchasing new equipment, however, will
depend on whether his company is awarded the grant he applied for. Many
other companies applied for the same grant.
This is an example of a project
O
A. risk
O
B. security
O
C. constraint
D. milestone

User Ratnanil
by
6.5k points

2 Answers

3 votes

Answer:

C

Step-by-step explanation:

trust

User Diahann
by
6.8k points
1 vote

Answer:

The correct answer is C

Step-by-step explanation:

Constraint is the term which is defined as something which will controls or limits the person or an individual what the person can do. Their decision depends or grounded on the constraint.

In this case,Oliver wants to buy the new equipment in order to complete the project. The budget is depend or grounded on the grant awarded by the company. So, it is an example of a constraint project.