150k views
4 votes
Please give examples of circumstances in which a project would employ lag relationships between activities using: a. finish to start. b. finish to finish. c. start to start. d. start to start.

User VBobCat
by
4.1k points

1 Answer

2 votes

Answer: Let's use a building construction as an example of a project.

Step-by-step explanation:

Lag is the delay of a successor activity and represents the time between this activity and a previous activity.

Finish to start: means a predecessor activity A must finish before the successor activity B starts. An example is constructing the roof a building before painting the interior.

Finish to finish: means the predecessor activity must finish for the successor activity to finish. An example is laying plumbing pipes and inspecting the plumbing pipes.

Start to start: means the predecessor activity must start for the successor activity to start. An example is writing a brochure to sell out buildings and the subsequent editing.

Start to finish: means the predecessor activity must start for the successor activity to finish. An example is a construction supervisor A cannot leave his post until construction supervisor B resumes.

User Rejaul
by
5.0k points