Data provided in the question:
Number of workdays in a year = 250
Demand, D = 7,500 units
Ordering costs, F = $25.00 per order
Carrying costs, C = $9.00
Lead time = 4 days
Now,
Reorder point = Lead Time in days × Average Daily Demand
also,
Average Daily Demand = Demand ÷ Number of workdays in a year
= 7500 ÷ 250
= 30
Thus,
Reorder point = 4 × 30
= 120