You are a project manager for a growing dairy farm business. It offers organic dairy products regionally and is expanding its operations to the West Coast. It’s in the process of purchasing and leasing dairy farm businesses to get operations underway. The subproject manager in charge of network operations has reported some hardware problems to you. You’re also having problems coordinating and integrating other elements of the project. Which of the following statements is true?A. You are in the Direct and Manage Project Work process.B. Your project team doesn’t appear to have the right skills and knowledge needed to perform this project.C. You are in the norming stage of team development.D. Your project team could benefit from some team-building exercises.

User Zubergu
by
5.6k points

1 Answer

3 votes

Answer:

A) You are in the Direct and Manage Project Work process.

Step-by-step explanation:

Direct and Manage Project Work: When a project manager leads his team into performing the activities defined in the project management plan and implements changes in order to achieve the project's goals.

Probably the most difficult task in the Direct and Manage Project Work process is to coordinate and integrate all the elements of the project, and that is exactly what this project manager is facing right now.

User Loken Makwana
by
5.2k points