3 votes
Which of the following statements about decomposition is the least true? Decomposition involves structuring and organizing the WBS so that deliverables are always listed at level one. Decomposition is a tool and technique used to create a WBS. Decomposition requires a degree of expert judgment and also requires close analysis of the project scope statement. Decomposition subdivides the major deliverables into smaller components until the work package level is reached.

1 Answer

1 vote

Answer:

Decomposition subdivides the major deliverables into smaller components. It is a tool and technique of the Create WBS process and is isued to create a WBS.

Level two components might be deliverables, phases, subprojets, or some combination