At some point in the life of a project, the project manager determined the following data on a $1,250,000 authorized budget project: amount of earned value $350,000. At that point, the value of the planned work was $750,000, and actual cost was $750,000. Based on this information, the Schedule Performance Index for this project was: a. 0.28 b. 0.47 c. 0.53 d. 0.60

User Tridy
by
9.4k points

1 Answer

6 votes

Answer:

Schedule Performance Index (SPI) = 0.47

so correct option is b. 0.47

Step-by-step explanation:

given data

authorized budget project = $1,250,000

amount of earned value = $350,000

value of the planned work = $750,000

actual cost = $750,000

to find out

Schedule Performance Index SPI for this project was

solution

we find schedule performance index (SPI) that is express as

Schedule Performance Index (SPI) = Earned Value of work ÷ Value of Planned Work ......................1

put here value we get

Schedule Performance Index (SPI) =
(350000)/(750000)

Schedule Performance Index (SPI) = 0.47

so correct option is b. 0.47

User Nevedha Ayyanar
by
7.9k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories