A customer desires to mix her own concrete. The clerk knows that the ratio of cement to sand to gravel is 1:3:4. If the customer needs 1000 pounds of dry mix, how many pounds of each ingredient should she use.

User Marc Ster
by
7.3k points

1 Answer

7 votes

Answer:

The quantity of cement use is 125 pounds

The quantity of sand use is 375 pounds

The quantity of gravel use is 500 pounds

Explanation:

Given as :

The ratio of cement to sand to gravel = 1 : 3 : 4

The total quantity of dry mix required = 1000 pounds

Let The quantity of cement required = 1 × x pounds

The quantity of sand required = 3 × x pounds

The quantity of gravel required = 4 × x pounds

So, According to question

The total quantity of dry mix required = The quantity of cement required + The quantity of sand required + The quantity of gravel required

Or, x + 3 x + 4 x = 1000 pounds

Or, 8 x = 1000 pounds

∴ x =
(1000)/(8)

I.e x = 125

So , The quantity of cement required = 1 × 125 pounds = 125 pounds

The quantity of sand required = 3 × 125 pounds = 375 pounds

The quantity of gravel required = 4 × 125 pounds = 500 pounds

Hence The quantity of cement use is 125 pounds

The quantity of sand use is 375 pounds

The quantity of gravel use is 500 pounds