Sally can paint a room in 5 hours while it takes Steve 3 hours. How long would it take them to paint if they worked together

User Alan Kent
by
8.0k points

2 Answers

5 votes
It would be 8 hours because you are adding 5 and 3 to get a total
User Tkingovr
by
8.2k points
3 votes

Answer: it will take them 1.875 hours to paint if they worked together

Explanation:

Sally can paint a room in 5 hours. This means that in 1 hour, 1/5 of the room. Her unit rate is 1/5

Steve 3 hours to paint the same room. It means that his unit rate per hour is 1/3

If they work together, it would take a lesser time because they would be working simultaneously and at their individual rates. It means that their rates are additive. Their combined individual rate will be 1/5 + 1/3

Assuming they worked together and finished the painting in t hours, their combined rate per hour will be 1/t. Therefore

1/5 + 1/3 = 1/t

3 + 5/15 = 1/t

8/15 = 1/t

8t =15

t = 15/8 = 1.875 hours

User Snild Dolkow
by
8.0k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories