Answer:
B. 14
Step-by-step explanation:
ES = early start
ES = finished point of the predecessor activity
Considering we have two activities which are:
5-7 which is expected to start at 6 and finish in 5 thus It will end at 11
6-7 which is expected to start at 7 and has a duration of 7 thus, ending at 14
The 7-8 activity will start as soon as the precedecessor end. These activities are finished at point 14 thus, that is the earliest activity 7-8 can start.