Tile & Grout (T&G) contracts to resurface the insides of the pools at WaterWorld Park. T&G knows that without the resurfacing, WaterWorld will have to delay its seasonal opening. T&G does not perform as promised. As consequential damages, WaterWorld can recoverA) the cost of new poolsB) the difference between T&G's price and the eventual cost of resurfacing.C) the loss of profit from the delayed opening.D) nothing.

User Webomatik
by
6.2k points

1 Answer

5 votes

Answer:

The answer is Letter C

Step-by-step explanation:

Water World can recover the loss of profit from the delayed opening.