Answer: B
Step-by-step explanation:
Control. Benefits. Cost. Net
A. (96/100*300,000)
288,0000.( 18,000.) 270,000
B. ( 94/100*300,000)
282,0000. (10,000) 272,000
C 97.5/100*300,000
292,500 (26,000) 266,500
The cost benefits analysis compares the cost to the benefits to be derived from a project and chosed the project with the highest benefits.
The reduction in the exposure means the reduced percentage is a benefit and the amount spent is a cost, subtracting the cost from the benefits gives us net benefits and the project with the highest net benefits is chosen for implementation.