Answer:
The BCWS is also known as Planned Value (PV).
So, in this way, PV = 3.125.000
Step-by-step explanation:
With the data we can obtain the PV as follows:
First, let's calculate EV as EV = CV + AC.
EV = -500.000 + 4.000.000 = 3.500.000
After this, we can calculate PV with this formula: SPI = EV/PV
PV = EV/SPI
PV = 3.500.000/1.12 = 3.125.000
We can conclude, with these results, that the project actually is forward about the schedule but with an overcost about the budget. In other words, the project advance must be 41% but now is on 36% due to the negative variance on the costs (CV).