Answer:
$8,062,500
Step-by-step explanation:
Data provided in the question:
Amount for which the Shale Miner Co. acquired mineral rights = $60,000,000
Estimated amount of resources to be recovered = 80,000 tons
Amount of resources mined during the year = 10,750 tons
Now,
Cost per ton of the resource mined
= ( Right acquiring amount ) ÷ ( Estimated amount of resources to be mined)
= $60,000,000 ÷ 80,000 tons
= $750 per ton
Therefore,
The amount of depletion for the current year
= Resources mined during the year × Cost per ton of the resource mined
= 10,750 tons × $750 per ton
= $8,062,500