Answer:
633600 lb-ft.
Step-by-step explanation:
In a conservative field , work done does not depend upon the path followed. It depends only on the initial and final point . Here work done as asked in the question will be equal to lifting the object straight to height of 120 Ft
So work done
= mgh
= ( 140 + 25 ) x 32 x 120
= 633600 lb-ft.