Answer: $1,020
Step-by-step explanation:
= Machine setup for Job 971 * Budgeted machine setup cost
Budgeted Machine setup cost = 13,260/390 setups
= $34 per setup
Overhead cost for Job 971 is:
= 34 * 30
= $1,020