In the systems ___________ phase of the systems life cycle, the report should be prepared to present the costs versus the benefits and it usually concludes by recommending one of the alternatives.

1 Answer

0 votes

Answer: Planning or Preliminary Phase

Explanation: At this stage, the alternative solution, cost and benefit of the project is considered. It is the first phase in the system life cycle process.

Here, it is identified if there is actually a need and how to determine the way out for the need.

At this stage, alternative solutions are stated, with associated costs as well as benefits to be derived from picking any of the available options.

thereafter, a recommendation is given as to the best option to be considered.