Answer:
2.64 minutes per cycle
Step-by-step explanation:
Total work time = 367 minutes per day
Break time = 17 min*3 = 51 min
Lunch time = 60 min
Total time left = 367 - 51 - 60 = 256 min
Demand = 97 jobs a day
Takt time = Total production time available/Demand
Takt time = 256 / 97
Takt time = 2.639175257731959
Takt time = 2.64 minutes per cycle