Answer:
PROJECT A
Year Cashflow [email protected]% PV
$ $
0 (87,000) 1 (87,000)
1 32,600 0.9158 29,855
2 35900 0.8386 30,105
3 43,400 0.7679 33,326
NPV 6286
PROJECT B
Year Cashflow [email protected]% PV
$ $
0 (85,000) 1 (85,000)
1 14,700 0.8873 13,043
2 21.200 0.7873 16,691
3 89,800 0.6986 62,734
NPV 7,468
Project B should be accepted because it has the higher NPV
Step-by-step explanation:
In obtaining the net present value, there is need to discount the cashflow for each year at the required rate of return of each project. The discount factor can be calculated as (1+r)n. Thereafter, the net present value is computed as the difference between the present value of cashflow and initial outlay.