The management team has asked you to reschedule the project so it finishes two weeks earlier without spending more money. They haven't removed any requirements from the project. Which technique would you use to shorten the project?

User Lotoya
by
8.7k points

2 Answers

5 votes

Answer:

Fast Track

Step-by-step explanation:

User Lesha
by
7.5k points
4 votes

Answer:

Crash the schedule

Step-by-step explanation:

Crashing is the method to utilize when optimizing has not spared enough time on the calendar. It is a method wherein assets are added to the venture for the least cost conceivable.

Cost and schedule tradeoffs are broke down to decide how to acquire the best measure of pressure for the least steady cost.