Answer:
4 hours
Explanation:
We can use rate-work formula shown below:
RWT = J
Where
R is the Rate
W is the number of workers
T is the time
J is the Job
Given,
W = 8
T = 6
J = 1 (we consider the task as "1" task)
Substituting, we find R:
RWT = J
R(8)(6) = 1
48R = 1
R = 1/48
Now, we need to find the time. Given:
W = 12
T = ?? (we want to find)
J = 1 (same task)
R = 1/48 (just found)
Substituting, we find our answer:
RWT = J
(1/48)(12)T = 1
(1/4)T = 1
T = 4 hours