The Princeville Company placed five (5) orders for Product 12B from Brookston Corporation. Brookston has the following information about Product 12B: Activity Cost Pools Activity Rate Product 12B Activity Machine Setups $ 12.00 per Machine hour 40 MHs Customer Orders $ 10.00 per Order 5 Orders What is the overhead cost assigned to Princeville for their five (5) orders of Product 12B?

A. $480
B. $530
C. $2,650
D. $990

User Mcjudd
by
7.1k points

1 Answer

3 votes

Answer:

B. $530

Step-by-step explanation:

Please see attachment