Answer:
201 hours.
Step-by-step explanation:
Given: Order size of work for a week is 2000 units.
Setup time is 1 hour.
Now, lets calculate the capacity requirement for a week at work centre B.
Formula; Capacity=
![[set\ up\ time+(labour\ per\ unit * total\ unit\ of\ work)]](https://img.qammunity.org/2020/formulas/business/high-school/uaq2uxsl43dqmycgm0o2bp8a5frs47k1ro.png)
Substitute the value in the formula.
⇒Capacity=
![[1+ (0.10 * 2000)]](https://img.qammunity.org/2020/formulas/business/high-school/jwrrjju01cilf02h75ibhgody86etxmmkm.png)
⇒ Capacity=
![[1+(200)] = 201\ hours](https://img.qammunity.org/2020/formulas/business/high-school/41oh5jaqgmysaze80s0xrhfg93xblduw5u.png)
∴ 201 hours is the capacity requirement for a week at work centre B.