Answer:
$60
Explanation:
Let the company's fixed charge be "x"
And let the the hourly rate be "h"
Firstly, 2 hours + fixed = $110, we can write:
2h + x = 110
Next, 3 hours + fixed = $150, we can write:
3h + x = 150
We multiply the first equation by "-1" to get:
-1 * [2h + x = 110] = -2h - x = -110
Now we add this equation to the 2nd:
3h + x = 150
-2h - x = -110
-------------------
h = 40
Hence, the hourly rate is $40
So, it would cost 1.5 * 40 = $60 for 1.5 hours