An assembly line pulls containers of parts from machining centers at a rate of 600 per day. Each container holds 20 parts and typically waits 2 hours at a machining center before it is processed. The setup and processing time for 20 parts is 6 hours. How many containers are needed if the safety margin is 10%?

User Querenker
by
4.9k points

1 Answer

4 votes

Answer:

Please see attachment

Step-by-step explanation:

Please see attachment