Answer:
Step-by-step explanation:
The preparation of the direct labor budget is shown below:
Culver Company
Direct labor budget for six months
June 30, 2017
Particulars Quarter 1 Quarter 2 Six month
Production
units (A) 5,590 6,600
Direct labor
Hours (B) 2.0 2.0
Labor wage
rate per hour (C) $16 $16
Total labor cost (A × B× C) $178,880 $211,200 $390,080
Six month is a sum of quarter 1 and quarter 2