233k views
1 vote
The _____ for an activity is the latest possible time an activity might begin without delaying the project finish date.

a. late start date.
b. early finish date.
c. early start date
d. late finish date

User Manjoor
by
5.3k points

1 Answer

2 votes

Answer:

The correct answer is A that is late start date.

Step-by-step explanation:

Late start date is the filed which comprise of the latest date on which a task could be started without delaying the finish of the project.

The date is grounded on the date when the task is started and also on the late start of the task, late finish dates of the tasks predecessor and the successor as well and also on other constraints.

So, the late start date for the activity is the latest possible time.

User Johanandren
by
5.4k points