A doll factory needed to produce an order of dolls for a shop. The factory

planned to spend 24 days on the production at a rate of 1,500 dolls per
day. Due to a technical improvement, the factory produced the dolls 1.6
times as fast as it normally would. How many days did it take the factory
to finish the order of dolls?​

User AGleasonTU
by
4.3k points

2 Answers

2 votes

Answer:

15 days.

Explanation:

By proportion, that is 24 / 1.6

= 15 days.

User Wykk
by
4.8k points
5 votes

24 / 1.6 = 15

Answer: 15 days