Answer:
$8,000
Step-by-step explanation:
To compute the total cost, first we have to calculate the fixed cost and the variable cost per hour by using high low method is shown below:
Variable cost per hour = (High manufacturing cost - low manufacturing cost) ÷ (High units produced - low units produced)
= ($8,150 - $6,500) ÷ (7,800 units - 4,500 units)
= $1,650 ÷ 3,300 units
= $0.5
Now the fixed cost equal to
= High manufacturing cost - (High units × Variable cost per unit)
= $8,150 - (7,800 units × $0.5)
= $8,150 - $3,900
= $4,250
To produce the 7,500 units, the total manufacturing cost would be
= Fixed cost + number of units produced × Variable cost per unit
= $4,250 + 7,500 units × $0.5
= $4,250 + 3,750
= $8,000
This is the answer and the same is not provided in the given options