Answer:
The labor time variance is 7,800 U.
Step-by-step explanation:
Calculate the standard hour.
Standard hour=Unit produced Labor standard per hour
=1,000x 7.6
= 7,600
Therefore, the standard hour is 7,600.
Explanation | Common mistakes | Hint for next step
The standard hour is calculated by multiplying units produced with labor standard per hour. The unit produced is 1,000 unit and labor standard per hour is 7.6 hours, so the standard hour is 7,600.
Step 2 of 2
Calculate the labor time variance.
Labor time variance =(Actual hour-Standard hour) Standard rate
=(8,200-7,600) $13
=600x$13
= 7,800 Unfavroable
Therefore, the labor time variance is 7,800 Unfavorable