Three workers can load a truck in 8 minutes. How many workers need to join this team so that they can load that truck in 6 minutes?

2 Answers

3 votes

Answer:

1 more worker should join

Explanation:

User Kyle Higginson
by
9.1k points
1 vote

Answer:

1 extra worker

Explanation:

If three workers load the truck in 8 minutes we have that:

3 workers = 8 minutes

We know that if we wanted to reduce the time at, for example, half, we would need to increase the workers in a half. More generally, if we want to reduce the time in 1/X me need to multiply the workers by X.

Here me need to reduce the time in 6/8 as 8*6/8 = 6. So, we will need:

3*8/6 = 24/6 = 4 workers.

So, we will need 1 more worker as we already have 3.