An MRP system that is updated periodically to account for all changes which have occurred within a given time interval is called a(n) ________ system.A. peggingB. regenerativeC. net-changeD. exception reportE. planned order release

1 Answer

2 votes

Answer:

B) regenerative

Step-by-step explanation:

A material requirements planning (MRP) system is used to merge several production activities into one single system that controls production and inventory. It's similar to ERP systems but it only focuses on the production area of a company. Using MRP systems enables production planning, scheduling, and control of production inputs (e.g. materials).

All MRP systems should be regularly updated in order to be efficient.