Answer:
First we have to find the Weighted average cost of capital of the firm. The formula for that is
(Cost of equity * percentage of equity) + (cost of preferred stock * percentage of preferred stock) + (cost of debt * percentage of debt*(1-tax rate)).
We put the values given to us in the question in this formula to find the weighted average cost of capital of the firm.
(0.55*0.13)+(0.05*0.09)+(0.40*0.075*(1-0.39))
= 0.0943= 9.43%
The Weighted average cost of capital of the firm is 9.43%, because the company is considering a project which is equally as risky as the overall firm, we can use the weighted average cost of capital is the internal rate of return of the project, so the internal rate of return of the project (WACC) is 9.43%.
Now in order to find the present value of the project we will discount the cash flows of the project using the IRR
Cash flow 0 = -325,000+
Cash flow 1= 87,000/1.0943
Cash flow 2= 279,000/1.0943^2
Cash flow 3= 116,000/1.0943^3
NPV= 76,011
The present value of the project is 76,011 when we discount the cash flows using an IRR or 9.43% which is also the WACC of the firm
Step-by-step explanation: