25.8k views
1 vote
Marko Shioda, master scheduler at Randall Manufacturing Company, prepared the following MPS for one of the firm's major end products, the Genuine Whatcha Macallit.

Week # 1 2 3
MPS 150 120 50

Mariko is concerned about this schedule’s impact on Widgets. It takes 3 Widgets to make each WhatchaMacalit. The two bottleneck work centers for producing Widgets are the "paint" work center and also the "final test" work center. The production manager has indicated that testing each Widget requires 0.3 hours and painting each Widget requires .5 hours. Calculate the labor hours needed (rough-cut capacity analysis) for the "paint" work center.Week # 1 2 3Widget paint

1 Answer

1 vote

Answer:

Step-by-step explanation:

MPS Week 1 = 150

It takes 3 widgets for 1 WhatchaMacalit.

Widgets required Week 1 = 150 *3 = 450

Painting hours required Week 1 = 450*0.5 = 225 hours

Painting hours required Week 2 = 120*3*0.5 = 180 hours

Similarly, Week 3 = 75 hours

Week # 1 2 3

Widget paint 225 180 75

User Charleshaa
by
7.0k points