In which phase does the development team check the project for error handling capabilities?

A , design
B, testing and delivery
C, development
D, maintenance

User Rebra
by
7.2k points

1 Answer

0 votes

Answer:

B

Step-by-step explanation:

engineers design and carry out test cases and evaluate exit criteria (by following the scope set in the planning phase). They create bug reports describing detected defects and report to the stakeholders on the test findings and the completion status. Testing may be repeated to check for errors.