Answer:
D. Re-order point = 26 days
Step-by-step explanation:
Given,
Annual Demand, D = 2,080 units
Number of working days = 320 days
Lead time = 4 days
We know,
Re-order point = (Annual demand/Number of working days)*Lead Time
Re-order point = (Annual demand/Number of working days)*Lead Time
Re-order point = (2,080/320)*4
Re-order point = (6.5*4)
Re-order point = 26 days
Therefore, the answer choice is D.
As there is no maximum and average lead time and no replenishment stock, I exclude the safety stock from the re-order point calculation.