Which of the following statements is NOT true?

A. A net requirements plan adjusts for on-hand inventory.
B. Distortion can be minimized when safety stock is held at each workstation, rather than at the finished goods or raw material levels.
C.MRP software programs are popular because manual approaches are slow and error-prone.
D.Gross material requirements assume that there is no inventory on hand.

1 Answer

3 votes

Answer:

B. Distortion is minimized when the safety stock is held at finished goods and raw materials stage.

Step-by-step explanation:

Distortion is minimized when the safety stock is held at finished goods and raw materials stage.